Home › Reference › All-in rates: architecture

All-in rates: architectural works

Trade rates for the architectural works of a building in the Klang Valley: roof coverings, waterproofing, brickwork, plastering and painting, floor and wall tiling, ceilings, doors and windows, sanitary fittings and metalwork.

RINGGIT MALAYSIA · KLANG VALLEY · UPDATED SEPTEMBER 2026

Architectural work is the reverse of structure: many items, each with a small quantity, so the rates matter more than the arithmetic. These are the rates we see for the ordinary specification of a Klang Valley factory, office or house: clay bricks, cement-and-sand plaster, emulsion and weather-resistant paint, ceramic and homogeneous tiles, gypsum ceilings, aluminium windows and mid-range sanitary ware.

Doors and windows are given per square metre of opening where the tender priced them per unit, because that is the figure that carries from one project to the next; multiply by the opening size on your schedule. Sanitary fittings are supply and install for mid-range brands; designer ranges can be several times these figures.

Rates are in Ringgit Malaysia for the Klang Valley and come from tenders and subcontractor quotations priced by WE Quantity Surveyor for recent projects. They are all-in rates at the trade level: material, labour, plant and wastage are included; the main contractor's profit and attendance, preliminaries (unless the page is about preliminaries) and any applicable SST are not. Where a range is shown, the low end is usually a large, simple job and the high end a small or awkward one. Use them to check a budget or a tender, not in place of a quotation for your own project.

Roof coverings

Roof coverings: all-in rates, RM, Klang Valley, September 2026
ItemUnitRate (RM)Notes
Metal roof decking, 0.47 to 0.48 mm colour-coated steel, on purlinsm²75 – 85
Metal decking as side cladding or fascia sheet, 0.40 to 0.48 mmm²75
Translucent fibreglass sheeting, extra overm²220 – 250
Rockwool insulation 50 mm under roof deckingm²28
Double-sided aluminium foilm²12 – 15
Wire mesh to support insulationm²3.5
Rockwool and foil as one itemm²40
Ridge cappingm45 – 55
FlashingZinc at the low end, colour-coated steel at the high endm65 – 120Zinc at the low end, colour-coated steel at the high end
Gutter, galvanised iron or zincm180 – 320
Rainwater downpipe uPVC 100 mmm100
Rainwater downpipe uPVC 150 mmm160
Rainwater downpipe uPVC 200 mmm120 – 220
Light-weight steel roof trusses, residentialm²80 – 90
Concrete roof tiles including battensm²45 – 50
Ridge or verge tiles, extra overm55
Aluminium foil sarking, double-sided, fire-retardantm²15
Hardwood fascia board 25 x 200 mm, gloss paintedm38
Stainless steel valley gutter, extra overm75

Waterproofing

Waterproofing: all-in rates, RM, Klang Valley, September 2026
ItemUnitRate (RM)
Cement and sand screed to falls, to receive waterproofingm²25 – 35
Waterproofing membrane or coating to flat roofs and wet areasm²35 – 48
Waterproofing upturn 300 mm high with angle filletm14 – 15
Protection screed 50 mm over waterproofingm²50
Ponding testitem50 – 200

Brickwork

Brickwork: all-in rates, RM, Klang Valley, September 2026
ItemUnitRate (RM)
100 / 115 mm clay brickwall in cement mortarm²50 – 60
200 / 230 mm clay brickwall in cement mortarm²100 – 110
Damp-proof course 100 mm widem1.5 – 3.0
Damp-proof course 200 mm widem3 – 5
RC lintol, small section, including reinforcement and formworkm50 – 60
RC coping or stiffener, small sectionm50

Plaster and paint

Plaster and paint: all-in rates, RM, Klang Valley, September 2026
ItemUnitRate (RM)
Cement and sand plaster 20 mm to internal wallsm²30 – 36
Cement and sand plaster to external wallsm²32 – 38
Cement and sand plaster to ceilings and soffitsm²32 – 38
Skim coat to concrete soffitm²11
Skim coat to plastered wall, residentialm²20
Groove lines in plaster, extra overm5
Cement render to aprons and drainsm²28
Emulsion paint, one sealer and two coats, large commercial or industrial areasm²5.5 – 6.0
Emulsion paint, small residential jobm²18
Weather-resistant exterior paint, industrialm²9.5
Weather-resistant exterior paint, residentialm²20
Aluminium composite panel cladding on sub-framem²340 – 380
Aluminium louvres or sun-shading finsm²450 – 500

Floor and wall tiles

Floor and wall tiles: all-in rates, RM, Klang Valley, September 2026
ItemUnitRate (RM)
Cement and sand screed 20 mm to receive tilesm²25 – 30
Ceramic tile 300 x 300 mm to floors or walls, including beddingm²85 – 100
Homogeneous tile 600 x 300 mm to floors or wallsm²70 – 80
Porcelain tile 600 x 600 mmm²100 – 105
Non-slip ceramic tile to wet areasm²85
Tile skirting 100 mm highm15 – 20
Tiles to stair treads, 255 to 300 mm widem25.5
Tiles to stair risers, 170 mm highm17
Nosing tiles to stair treadsm32

Ceilings

Ceilings: all-in rates, RM, Klang Valley, September 2026
ItemUnitRate (RM)
Gypsum plaster ceiling board 9 mm on metal suspension systemm²45 – 60
Moisture-resistant plaster ceiling to wet areasm²55 – 65
Cement board ceiling 9 mm to external soffitsm²85
Access panel 450 or 600 mm square, extra overno.80

Doors and windows (supply and install)

Doors and windows (supply and install): all-in rates, RM, Klang Valley, September 2026
ItemUnitRate (RM)
Timber flush door 915 x 2135 mm with frame, ironmongery and paintno.530 – 760
Timber door 760 x 2135 mm to toiletsno.540
Fire-rated door, 1 hour, single leaf, with frame and closerno.850 – 1,140
Fire-rated door, 2 hour, single leafno.1,040 – 1,140
Aluminium-framed glass door, 6 to 8 mm clear glassm²580 – 600
Aluminium-framed windows (casement, top-hung, fixed) with 6 mm clear glassm²480 – 550
Stainless steel door 900 x 2400 mm, residentialno.1,300
Mild steel roller shutter, large industrial (about 9 m x 5 m)m²380 – 420
Metal sliding door, large industrialm²480 – 520

Sanitary fittings (supply and install)

Sanitary fittings (supply and install): all-in rates, RM, Klang Valley, September 2026
ItemUnitRate (RM)
Water closet, close-coupled, mid-rangeno.530 – 700
Squatting panno.650
Wall-hung wash basinno.290 – 400
Stainless steel sinkno.290 – 460
Basin tapno.125 – 235
Bib tapno.70 – 135
Sink tapno.125 – 300
Shower set with mixerno.210
Hand bidetno.80
Toilet paper holderno.57 – 106
Stainless steel floor trapno.23 – 73
Mirror 750 x 750 mmno.250 – 300
Grab bar to OKU toiletno.800 – 850
Cold-water plumbing, per pointpoint1,800
Soil, waste and vent piping, per pointpoint800

Metalwork and sundries

Metalwork and sundries: all-in rates, RM, Klang Valley, September 2026
ItemUnitRate (RM)
Mild steel railing or handrail 900 mm highm220
Glass canopy on steel framem²1,500
Squatting pan base (raised platform)no.350

Questions we get asked

What does supply and install include?
The item delivered to site and fixed complete: for a door, the leaf, frame, architrave, ironmongery and paint; for a window, the aluminium frame, glass, gaskets and sealant; for a WC, the pan, cistern, seat and connection to the waste. Plumbing pipework to the fitting is priced separately, per point.
Why are doors and windows priced per square metre?
A door or window schedule changes with every project, but the rate per square metre of opening for the same specification hardly moves. Aluminium windows with 6 mm clear glass, for instance, price at roughly the same figure per square metre whether the window is 600 x 600 or 4500 x 2745, so the per-metre rate is the one worth carrying in a rate library.
Do these rates include the screed under the tiles?
No. Screed, tiling and skirting are separate items, as they are in the bill. A tiled floor in a house is screed at about RM 25 to 30/m² plus tiles at RM 85 to 100/m² plus skirting per metre; quoting it as one number hides where the money goes when the tile is changed.

Need these rates applied to your drawings?

WE Quantity Surveyor measures and prices bills of quantities for contractors, developers and consultants across Malaysia and Singapore. Fixed fee, quoted within 24 hours.

Get a fixed-fee quote

Measuring the quantities yourself?

Take-Off by WEQS is our on-screen measurement software for Windows: open the PDF or CAD drawing, trace what you need, export to Excel. Free for 30 days, every feature on.

Try Take-Off by WEQS

Rates compiled by WE Quantity Surveyor, a BQSM-registered quantity surveying practice in Kuala Lumpur, from its own tender pricing. They are published as general guidance for the Malaysian construction industry; no liability is accepted for their use on any particular project. Reproduction with a link to this page is welcome.