Preliminaries rates, Malaysia
What the preliminaries of a Malaysian building contract cost, item by item: hoarding and signboard, site office and kongsi, erosion control, temporary services, supervision, insurances and bonds, statutory levies, plant and scaffolding, and what preliminaries come to as a share of the contract sum.
Preliminaries are the contractor's costs of running the site rather than building the work: the things the bill lists before the trades start. On a Malaysian tender they are either priced as a lump sum against the specification or itemised, and the itemised bill is the one a quantity surveyor can check line by line and value month by month.
The table gives the rates we see priced against those items on Klang Valley tenders. Lump-sum items are for a medium project (RM 5 to 20 million, 12 to 18 months) unless the item says otherwise; the percentages are of the contract sum.
Rates are in Ringgit Malaysia for the Klang Valley and come from tenders and subcontractor quotations priced by WE Quantity Surveyor for recent projects. They are all-in rates at the trade level: material, labour, plant and wastage are included; the main contractor's profit and attendance, preliminaries (unless the page is about preliminaries) and any applicable SST are not. Where a range is shown, the low end is usually a large, simple job and the high end a small or awkward one. Use them to check a budget or a tender, not in place of a quotation for your own project.
Site establishment
| Item | Unit | Rate (RM) | Notes |
|---|---|---|---|
| Site hoarding, 2.1 to 2.4 m high metal deck sheeting on steel posts with concrete footing, including maintenance and removal on completionResidential at the low end, factory and warehouse sites at the high end | m | 280 – 380 | Residential at the low end, factory and warehouse sites at the high end |
| Extra over hoarding for a double-leaf site access gate | no. | 3,000 – 6,000 | |
| Project signboard to local-authority requirements: supply, erect, maintain and remove | no. | 5,000 – 8,000 | |
| Site office and toilet, small project, for the contract periodCabin, sanitary connection and cleaning | item | 5,000 – 10,000 | Cabin, sanitary connection and cleaning |
| Kongsi (workers' quarters) and site store, medium project | item | 30,000 – 40,000 | |
| Temporary works and services: access road, temporary drains and culverts | item | 10,000 – 30,000 | |
| Levels and setting out of the works by a licensed surveyor, medium project | item | 20,000 – 30,000 | |
| General site clearance of light vegetation and debris, including cart away | m² | 5 – 10 |
Erosion and sediment control (ESCP)
| Item | Unit | Rate (RM) | Notes |
|---|---|---|---|
| Wash trough (wheel wash) at the site exit, including maintenance | no. | 20,000 – 30,000 | |
| Silt trap, including maintenance and desiltingSmall residential site at the low end | no. | 3,000 – 10,000 | Small residential site at the low end |
| Sediment (silt) fence | m | 35 – 40 | |
| Earth drain with earth bund | m | 45 – 55 | |
| Check dam | no. | 80 | |
| Gabion basket 1 m x 1 m x 1 m, filled with rock | no. | 220 – 260 |
Temporary services
| Item | Unit | Rate (RM) |
|---|---|---|
| Temporary electricity supply, distribution boards and lighting, medium project, for the contract period | item | 15,000 – 25,000 |
| Temporary water supply, medium project, for the contract period | item | 5,000 – 10,000 |
| Site security (guards), medium project, for the contract period | item | 20,000 – 30,000 |
Staff and supervision
| Item | Unit | Rate (RM) | Notes |
|---|---|---|---|
| Foreman-in-charge / site supervisor, full time for the contract period, medium projectSalary and on-costs | item | 120,000 – 150,000 | Salary and on-costs |
Insurances, bonds and statutory
| Item | Unit | Rate (RM) | Notes |
|---|---|---|---|
| Contractor's All Risks (CAR) insurance | % of contract sum | 0.15 – 0.25 | |
| Workmen's compensation / employer's liability insurance | % of contract sum | 0.08 – 0.10 | |
| Performance bond of 5% of the contract sum: cost of the bank guarantee or insurance bond for the contract period | % of contract sum | 0.3 – 0.5 | |
| CIDB levy (Act 520) on contracts above RM 500,000Statutory rate | % of contract sum | 0.125 | Statutory rate |
| Stamp duty on the contractAd valorem on the contract sum; confirm the current rate with the stamping office | % of contract sum | 0.1 | Ad valorem on the contract sum; confirm the current rate with the stamping office |
| Contract documents: printing, binding and signing sets | item | 10,000 – 16,000 |
Plant and scaffolding
| Item | Unit | Rate (RM) |
|---|---|---|
| Scaffolding for all trades, medium project: erect, hire for the contract period and dismantle | item | 50,000 |
| Plant and equipment (hoist, crane hire, compaction, generators), medium industrial project | % of contract sum | 1.5 – 2.5 |
Preliminaries as a whole
| Item | Unit | Rate (RM) |
|---|---|---|
| Preliminaries, small residential project (bungalow, RM 0.5 to 1 million) | % of contract sum | 8 – 10 |
| Preliminaries, factory or warehouse (RM 5 to 20 million) | % of contract sum | 5 – 8 |
Questions we get asked
- What percentage of the contract sum are preliminaries in Malaysia?
- Between 5% and 10% on most building projects. A factory or warehouse of RM 5 to 20 million usually prices at 5% to 8%; a small residential job runs higher, 8% to 10%, because the fixed costs (hoarding, signboard, site office, insurances) are spread over a small contract sum. High-rise work with tower cranes and hoists sits at the top of the range or above it.
- What is included in preliminaries?
- The items the contractor needs to run the site: site establishment (hoarding, signboard, offices, kongsi, stores), temporary services (electricity, water, security), setting out, erosion and sediment control, supervision and staff, insurances, the performance bond, statutory payments such as the CIDB levy and stamp duty, plant, scaffolding, and general obligations under the specification such as protection, cleaning and as-built records.
- Should preliminaries be a lump sum or itemised?
- Itemised, wherever the form of contract allows. A single lump sum for 'comply with the specification' cannot be checked against the market, and it cannot be valued fairly in progress claims. An itemised bill separates fixed charges (paid when the item is set up), time-related charges (paid monthly) and charges paid at completion, which is how the PAM and JKR forms expect preliminaries to be valued.
- How are preliminaries paid in progress claims?
- Fixed items such as hoarding, the signboard and the site office are paid when they are in place; time-related items such as supervision, security, temporary services and plant are paid month by month over the contract period; removal and final cleaning are paid at completion. Where the bill is a lump sum, the QS usually splits it on the same basis before the first claim.
Need these rates applied to your drawings?
WE Quantity Surveyor measures and prices bills of quantities for contractors, developers and consultants across Malaysia and Singapore. Fixed fee, quoted within 24 hours.
Get a fixed-fee quoteMeasuring the quantities yourself?
Take-Off by WEQS is our on-screen measurement software for Windows: open the PDF or CAD drawing, trace what you need, export to Excel. Free for 30 days, every feature on.
Try Take-Off by WEQSRates compiled by WE Quantity Surveyor, a BQSM-registered quantity surveying practice in Kuala Lumpur, from its own tender pricing. They are published as general guidance for the Malaysian construction industry; no liability is accepted for their use on any particular project. Reproduction with a link to this page is welcome.